Production Order Production Setup Time

 My client has a production setup where there is a particular activity which has a setup time of 8 hrs when it is executed for the first time, but if another production order is taken up for the same...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order Material Stock in Production Order

 I have the problem in stock against production order:
Our scenario is we don’t want to create a sales order. I create a production order that has 5 operations. The first operation is sub...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order Automatic Conversion to Production Orders

 Is there anyone out there who knows if it is possible to make an automatic change of planned orders to production orders right away - or perhaps even to skip the planned orders and create pp - orders...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order Regarding Production Order Confirmation

 Production order confirmation with future date is not allowed
Future dates can be configured in the confirmation configuration.
In configuration OPK4, define confirmation parameters.
When this...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order What is Backflushing?

 Can anyone tell me what is backflushing for? When is it use?
Back flushing is nothing but automatic goods issue. System will automatically posts the goods issue when you confirm the operations.You...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order How Costing takes place in Production Orders

 Can anyone please explain me the how the Costing takes place for the Production Orders.
Actually, I am new to this package , In Other Package (RAMCO ERP)
(The Process is like follows:
a....
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order SAP flow for REWORK activity

 What is the SAP flow for REWORK activity in PP-PI.
Sample Scenerio:
1. Initial Process Order qty: 10pc
2. Confirmed QTY.: 9 PCS.
3. Rejection qty .: 1 pc.
4. Now that one pc. is to be reworked in...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
Production Order Serial Number For Component

 I have a FG (A/C) which has a serial number. This A/c has a compressor in its BOM.
The client requirement is to link the compressor to A/c using serial number. So, I maintain serial number profile...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
How To Delete Old PP Production Orders

 How to delete old production orders ( CO78 )?
Note that CO78 is the start of the Archive process. We are not using Archiving yet but the initial process fits the bill for what we need to do as...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
SAP PP How to “permanently” delete new planned orders?

 Your company insists on fixing planned orders, to try to keep a stable, six-month plan. But you still get new planned orders generated in-between the fixed ones. You thought that you would get...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
SAP PP Planned Order Assign Multiple Planned Order to a Purchase Requisition

 In order to assign multiple planned order to a single purchase requisition number, you need to make used of the external purchase requisition number range.
Define your external purchase requisition...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
SAP PP Planned Order Conversion to Process Orders

 We are facing problems when converting planned orders to process orders. During conversion when BOM is re-exploded it is not using the same production version as specified in the planned order...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Why used Planning tools like APO or I2?

 APO and I2 are Finite PLANNING tools. When MRP runs with APO or I2 (or Red Pepper or Manugistics), it takes Capacity issues into consideration. MRP in SAP R/3 Core does not, it assumes infinite...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Difference between MRP vs MPS

 Explain the difference between MRP & MPS. Though both components gives you the requirement list, what we gain out of MPS run rather than running MRP. What is the main idea behind this?
The...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
SAP PP MRP Factory Calendar

 Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.
You can create your company factory calendar via transaction code 'SCAL'.
Assignment of the...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP GR processing time in PP and MM

 I have one material number that is procured externally but also produced inhouse. Now I have one problem with the GR processing time. As far as I can see the parameter on the material master on MRP2...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Calculation to determine the delivery date and release date

 There have been three parameters that SAP will take it into calculation to determine the delivery date and release date during material requirement planning. They are -
1) Planned Delivery Time...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Purchasing processing Time - OPPQ

 Please refer above subject and would like to do following. External Processing Time I have set in using OPPQ. My client want this time set differently for different Vendor. Is there any userexit or...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Define Safety Stock Availability

 The IMG can be set in SM30 - V_438M_S
You define per plant and per MRP group the percentage of the safety stock that is to be available for planning. This helps to avoid a situation where order...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Questions on MRP Group and MRP Controller

 MRP groups are used when the plant division for planning is not enough for the division of the different materials MRP requirements. You assign different groups according to the requirements to run...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Planning separately via Storage Location or Vendor with MRP Area

 Steps 1 :-
You must convert the existing planning file (table MDVM) to the new planning file (table DBVM)
in order to be able to use MRP areas in materials requirements planning. Transaction...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP - The Common Planning Strategy used

 The planning strategies are maintained in Customizing for Demand Management in SM30 - V_T461S.
Define the Planned Requirement Type and assign the requirement class in OMP1.
Define the requirement...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Why Planning file entry still Exists?

 Does anyone know why a planning file entry would exist for NETCH or NETPL when there has been NO activity on the material since the last planning run? No movements, no PO's created, no Orders taken,...
SAP,ABAP PROGRAMMING,Reports,Bdc,SAP Scripts,Smart Forms,Module pool,ALV Interactive, Classic reports,ALE,EDI,Work Flow,User Exits,Customer Exits,BADI,BAPI
PP MRP Planning Strategy Selection

 Selection priority for planning strategy is:
First material, second MRP group and last plant parameters. E.g. System first checks for material, if strategy is defined there, that is used, if it's...